Enerpac Integrated Hydraulic Solution for IRR Bangkok project
Movement of the world’s largest movable scaffolding system
An industrial ring road is constructed to relieve the traffic congestion in Bangkok’s main industrial areas. This large Bangkok IRR project includes two 700 meters long, 172 meters high cable stayed bridges connecting 13 kilometers of ring road. Hydraulic systems are designed to move the heaviest 1200 tons formwork travelers in South East Asia.

For allowing ships access to Bangkok’s harbour, the bridge deck of the intersection between the two cabled stayed bridges over the Chao Phraya River will be 50 m high.
There are many reasons for the environmental stress generated by modern urbanization. Around 400 – 600 vehicles are added to the streets of Bangkok everyday causing an ever increasing volume of traffic. This causes enormous traffic jams and subsequently a great deal of social and economic difficulties. Consequently the average travel speed in central Bangkok during peak hours is a mere 12 km/hr!
Therefore to make it easier for local residents and visitors alike to travel inside Bangkok, the infrastructure promised by the government of Thailand has to be fully developed to deal with the increasing number of people. Though it would not seem plausible to many, in fact Bangkok was the first Southeast Asian city to propose plans to introduce a system for the reduction of traffic congestion. Incidentally, Thailand was only the third Asian country, after Japan and Hong Kong to propose such a system. There are already in place various ways that are meant to reduce traffic congestion. Many bridges exist both within the city and its outlying suburbs. In place there is also the sky train which services the city center. 2004 saw the MRTA’s Bangkok subway system start operating for the first time. In an effort to tackle Bangkok’s perpetual traffic problems the government has also committed to expanding the road and railway system through massive expenditure in the coming decade.

Bridge sections of the IRR-Bangkok project under construction.
More impressive still is that this unique double bridge complex is built with and uses engineering solution unseen anywhere else in the world! For allowing ships access to Bangkok’s Klong Toey harbour coming up from the Chao Phraya River, the bridge will be 50 m high. Also due to the snaking course of the river on its way to the gulf of Thailand, the bridge will cross the Chao Phraya River not once but twice without touching the ground. Finally in mid air a full 50 meters up, an intersection between the two bridges will be built. This will allow motorists to go north without crossing the second bridge! The reason for this design is because the strip of land between parts of the river is incredibly narrow, making it impossible to construct a normal intersection.

Construction of the in situ decking of Bangkok’s industrial ring road

Pile caps and columns of the IRR mega-bridge project under construction.
This project is owned by the Public Works Department (PWD). The sections are divided into 3 contracts which are being worked on by two different contractor groups.
Both contracts number 1 and number 2 are for the Northern and Southern bridges and are being done by TNNS joint ventures. (Taisei / NKK Corporation / Nishimatsu and Sino Thai Construction)
While contract number 3 for the Western elevated interchange entrance and exits is being done by KTU joint ventures. (Tokyo Construction / Kajima and Unique Engineering)

In situ decking and movable scaffolding systems. The form for the V-part alone weighs over 60 tons.
With a proven track record for safety and reliability, Enerpac was chosen by main contractor, Taisei to design and supply the hydraulic systems to be integrated in the movable scaffolding system. The typical formwork arrangement requires 2 custom-built 7,5 kW low pressure hydraulic power units to actuate 24 pieces of 100 tons horizontal and 60 pieces vertical cylinders complete with clevis eye and mounting attachments to allow formwork pushing and pulling operations. On the 700 bar high pressure side, 4 pieces of specially designed Enerpac – CLL-25010, 250 tons capacity lock-nut jacks coupled with 2 units of standard RRH-6010 Hollow center jacks provide lifting, lowering and tensioning forces respectively on the main support of the formwork.
While on the(MSS) Movable Scaffolding System, a large quantity of different sets and sizes of integrated high and low pressure hydraulic pumps & cylinders provided solutions for various applications such as vertical nose adjustment, longitudinal & side launching as well as bottom slab folding plus rolling wagon operations. Just to name a few of its applications within it's intricate system. In one instance alone, 72 units of 50 tons low-pressure cylinders are used on the External formwork's vertical adjustment.
Being a global company, Enerpac hydraulics exercised close collaboration between its Japan, Singapore & Thailand offices, thus displaying great expertise in its system supply and commissioning.
Fostering good business relationships and regular follow-ups with all its major contractors at site also boosted confidence and reinforced the strong brand name that ENERPAC is recognized as a popular worldwide name.
