Turbine and Generator Installation at a New Power Plant in Libya

Customer

Sarilar Group

Location

Khoms, Libya

Challenge

Çal?k Enerji is constructing a new simple-cycle power plant with a 542 megawatt capacity in Khoms, Libya. The Sarilar Group was tasked with installing a GE gas turbine weighing approximately 280 tons and a GE generator weighing approximately 214 tons. Installation required lifting the turbine and generator over 5 meters high and lowering into position on a concrete foundation.

Solution

A SBL1100 hydraulic gantry was used to lift both the 280 ton turbine and 214 ton generator off an SPMT and position on the concrete foundation. The SBL1100 hydraulic gantry provided Sarilar Group the ability to maneuver the turbine and generator with precision; improving the safety and efficiency of the installation process.

Products

SBL1100 Hydraulische Portalkrane