Enerpac has gained unique expertise in delivering hydraulic solutions for the controlled movement and positioning of structures.
Repairing a Building's Foundation after an Earthquake
After a devastating earthquake, a 2,800 ton city center building was knocked off its foundation and needed to be lifted and leveled by up to 300 mm.
Infraestrutura
Replacing Bridge Bearings without Interrupting Traffic to the Second Bosphorus Bridge
Located on the O-2 Highway in Istanbul, the Sadabad Viaduct is a connecting motorway to the Second Bosphorus Bridge; the 19th longest suspension bridge span in the world. Approximately 400 bearings needed to be replaced on the Sadabad Viaduct while the road remained continuously open to traffic.
Pontes
Pulling Pins on an Oil Well Casing Elevator Spider
The borehole of every oil well drilled must be cased with a durable material to prevent contamination and provide structural support during drilling. An elevator spider is used as a guide to aid in centering each casing. The pin on the elevator spider must be replaced after every drill in order to remove corrosion, dirt and grime built up during drilling. MOISS’s existing process for removing the pin took up to 4 hours and required continuous hammering.
Óleo e Combustível
Lifting and Installing the Deck Sections of the Golden Horn Metro Bridge
The Golden Horn Metro Bridge is a 936 m (3,071 ft.) long cable-stayed bridge which spans the Golden Horn waterway in Istanbul, Turkey. Portions of the bridge deck rotate in order to permit large shipping vessels through the waterway. The rotating bridge deck segments were fabricated off-site and floated in on a barge. The 300 ton deck sections needed to be lifted off the barge nearly 17 meters and installed into position.
Pontes
Synchronous Lifting Pump and High Tonnage Cylinders Steady the Ship for Seaspan
Effective, safe, and precise movement of such a large and heavy object requires exact control and synchronized movement of all lifting points. To achieve this, an Enerpac EVO Synchronous Lifting Pump and 12 High Tonnage Hydraulic Lifting Cylinders were specified and supplied by local Enerpac distributor Hyseco.
Shipbuilding
Turbine and Generator Installation at a New Power Plant in Libya
Çal?k Enerji is constructing a new simple-cycle power plant with a 542 megawatt capacity in Khoms, Libya. The Sarilar Group was tasked with installing a GE gas turbine weighing approximately 280 tons and a GE generator weighing approximately 214 tons. Installation required lifting the turbine and generator over 5 meters high and lowering into position on a concrete foundation.
Geração de Força
Enerpac JS-250 Jack-Up System Deployed for Bridge Removal
The extension of Runway B at Narita Airport required the creation of a new grade-separated intersection between the Higashi-Kanto Expressway and the extended section of Runway B.
Infrastructure
O Sistema de Levantamento Sincronizado faz o lançamento de uma Plataforma de Petróleo Offshore de 43.000 ton
Levantamento, equilibrio e lançamento suave de um sistema de produção flutuante de petróleo de 43.000 ton para o campo de petróleo de Gurmusut-Kakap. Manter a integridade da estrutura durante o levantamento era essencial, não somente para proteger a segurança do levantamento, mas também para garantir a integridade estrutural e a segurança através de sua vida operacional.
Óleo e Combustível
A safe and efficient way of removing large diameter reamers with a SL100 Hydraulic Gantry System
The removal of raise bore reamers has traditionally been a hazardous, complex, costly and time-consuming process.
Mining
Installing Pylon Sections of a Cable-Stayed Bridge with a SyncHoist
Gotowski constructed a 200 meter long cable-stayed "University Bridge" to connect two parts of Bydgoszcz separated by the Brda River. The bridge's design requires the erection of two 68 meter tall pylons (towers) to support the bridge deck. Constructed in sections, the pylons weighed 90 to 130 tons and needed to be positioned with precise accuracy.
Pontes
Hydraulic Drive System for Las Vegas Observation Wheel
Erecting the Las Vegas High Roller Observation Wheel included installing the 28 passenger cabins. To ensure accurate and safe installation, a hydraulic drive system was needed to turn the wheel for correct positioning and placement. The drive system would also be critical in the overall rotation of the wheel, which would serve as the permanent operating system. Enerpac and Schwager Davis Inc., a specialty contractor, worked together to supply a reliable system solution.
Infraestrutura
Box Girder Launching System on the I-95 Whittier Bridge
Constructed in 1951, the John Greenleaf Whittier Bridge is currently in the process of being replaced by a new bridge compliant with current safety standards. The high traffic bridge connects Newburyport and Amesbury via I-95 over the Merrimack River. Walsh Construction is employing a rail mounted gantry crane system to simplify the placement of the steel bridge girders and precast deck to create the approach spans. Two 6 foot tall, 960 foot long temporary support steel box girders will be launched across temporary piers to create a rail system for the gantry crane to operate on during the approach span construction. The steel box girder arrangement will be moved after the placement of each approach span. It’s critical that the two 550 ton temporary steel support box girders move in unison in order to prevent binding or misalignment of the gantry crane operating on top of the rail system.